Executing an internal calibration activity with measurement data collection

Prerequisites

 

Introduction

If the Create activity automatically option is checked in the activity plan, the system will automatically create the calibration activity, sending it directly to the responsible technician. Thus, the steps in this article become useful for activity plans that do not have the automatic creation option checked, or for when an activity outside the frequency needs to be created.

In this article, as an example, internal calibration activities will be created from the plan configured in the previous step, the objective of which is to obtain the results of the measurement data collection.

 

Executing a calibration activity

Click here and watch the video to learn how to execute an internal calibration activity. Use a calibration plan with a standard activity and internal service center to create the activity. The completion of the calibration tables has been separated into other articles, which are also mentioned in the article to which you will be directed.

The mandatory steps described in the video for creating the records to be used in the internal calibration flow will be illustrated below, as an example.

 

Conclusion

Once all measurement results are entered and the execution is finished, the internal calibration flow will have been completed successfully! Access the other flows of the introduction article to learn how to use other resources of the Maintenance component.


Was this article helpful?